According to the Village Development Plan following are the main infrastructure related problems in the village.
1. Dilapidated condition of the village roads, including bridges and culverts.
2. Absence of a Playground
3. Lack of Safe Drinking Water.
The following steps have been completed:
1.Form Village Development Plan and select Sub Projects
2006.05.04
2.Elect Sub- Project Committees
2006.06.07
3.Recruit Technical Officers
2006.09.14
4.Prepare basic feasibility study report and get the approval
2006.09.14
5.Prepare estimates
2006.09.08
6.Obtain deposit certificate for 10 % community contribution
2006.09.16
7.Get the approval of Maha Sabha
2006.09.14
8.Appraise by the provincial Appraisal Team
2006.09.19
9.Direct to Gemidiriya to receive funds
2006.09.25
Development Proposals and Fund Allocations
Sub Project Title
Amount Allocated
Rs.
Beneficiary Households
Poor Beneficiary Households
Bridge
807,000.00
259
152
Play ground
368,200.00
259
152
Multipurpose Building
2,054,758.00
259
152
Water Project
1,441,299.00
62
32
Infrastructure sub project 1
Title of Sub Project:
Bridge
Reasons for Selecting this Project :
Transportation is the most serious issue faced by the people. It is difficult to travel and even walking during the rainy season. Community has to pay higher charges to transport their agro products to the market. The road becomes a water stream during the rainy season. Therefore, the first priority was given to the bridge/road project.
Estimates
Stage of Construction
Total Estimate (Rs.)
10% Cash Contribution (Rs.)
20% Labour Contribution (Rs.)
No: of Labour Days
Gemidirya Contribution (Rs.)
Labour
Goods
1st Stage
334,000.00
30,469.00
73,600.00
0.00
52
227,931.00
2nd stage
314,000.00
28,576.00
58,200.00
0.00
36
227,223.00
3rd stage
159,000.00
14,465.00
15,222.00
0.00
21
129,312.00
0.00
0.00
0.00
0.00
0
0.00
Total
807,000.00
73,510.00
147,022.00
0.00
109
584,466.00
Total Estimate Includes Civil works, Training, Payment for technical services, Contingencies, Administrative costs
Achievements
Stage
10% Cash Contribution
(Rs.)
20% Labour Contribution
(Rs.)
Fund received from
other sources
Gemidirya Contribution
(Rs.)
1st Stage
30,469.00
73,600.00
0.00
227,931.00
2nd Stage
28,576.00
58,200.00
0.00
227,223.00
3rd Stage
14,465.00
15,222.00
0.00
129,312.00
0.00
0.00
0.00
0.00
Total
73,510.00
147,022.00
0.00
584,466.00
Current Status
Stage 1:
Completed.
Stage 2:
Completed.
Stage 3:
Completed.
Infrastructure sub project 2
Title of Sub Project:
Play ground
Reasons for Selecting this Project :
The Children in the village needs a play ground to take part in sports activities and other common activities.
Estimates
Stage of Construction
Total Estimate (Rs.)
10% Cash Contribution (Rs.)
20% Labour Contribution (Rs.)
No: of Labour Days
Gemidirya Contribution (Rs.)
Labour
Goods
1st Stage
115,200.00
10,400.00
22,000.00
0.00
0
82,800.00
2nd Stage
138,000.00
12,720.00
32,000.00
0.00
0
93,280.00
3rd Stage
115,000.00
11,120.00
16,000.00
0.00
0
87,880.00
0.00
0.00
0.00
0.00
0
0.00
Total
368,200.00
34,240.00
70,000.00
0.00
0
263,960.00
Total Estimate Includes Civil works, Training, Payment for technical services, Contingencies, Administrative costs
Achievements
Stage
10% Cash Contribution
(Rs.)
20% Labour Contribution
(Rs.)
Fund received from
other sources
Gemidirya Contribution
(Rs.)
1st Stage
10,400.00
22,000.00
0.00
82,800.00
2nd Stage
12,720.00
0.00
0.00
0.00
3rd Stage
11,120.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total
34,240.00
22,000.00
0.00
82,800.00
Current Status
Stage 1:
Completed.
Stage 2:
75% on going.
Stage 3:
Infrastructure sub project 3
Title of Sub Project:
Multipurpose Building
Reasons for Selecting this Project :
The community needs a central place for them to maintain an office, conduct meetings and other activities.
Estimates
Stage of Construction
Total Estimate (Rs.)
10% Cash Contribution (Rs.)
20% Labour Contribution (Rs.)
No: of Labour Days
Gemidirya Contribution (Rs.)
Labour
Goods
1st Stage
1,519,545.00
128,919.00
257,838.00
0.00
0
1,132,788.00
2nd Stage
1,081,111.00
98,689.00
197,380.00
0.00
0
0.00
3rd Stage
187,144.00
17,214.00
17,000.00
0.00
0
152,929.00
0.00
0.00
0.00
0.00
0
0.00
Total
2,787,800.00
244,822.00
472,218.00
0.00
0
1,285,717.00
Total Estimate Includes Civil works, Training, Payment for technical services, Contingencies, Administrative costs
Achievements
Stage
10% Cash Contribution
(Rs.)
20% Labour Contribution
(Rs.)
Fund received from
other sources
Gemidirya Contribution
(Rs.)
1st Stage
128,919.00
257,838.00
0.00
1,132,788.00
2nd Stage
98,689.00
165,000.00
52,000.00
0.00
3rd Stage
17,214.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total
244,822.00
422,838.00
52,000.00
1,132,788.00
Current Status
Stage 1:
Completed.
Stage 2:
80% on going.
Stage 3:
Infrastructure sub project 4
Title of Sub Project:
Water Project
Reasons for Selecting this Project :
The community needs clean drinking water for the village. Therefore they decided to select the Water project as the 3rd priority.
Estimates
Stage of Construction
Total Estimate (Rs.)
10% Cash Contribution (Rs.)
20% Labour Contribution (Rs.)
No: of Labour Days
Gemidirya Contribution (Rs.)
Labour
Goods
1st Stage
649,011.00
55,601.00
0.00
0.00
0
593,410.00
2nd Stage
792,288.00
78,729.00
277,260.00
0.00
0
436,300.00
3rd Stage
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
Total
1,441,299.00
134,330.00
277,260.00
0.00
0
1,029,710.00
Total Estimate Includes Civil works, Training, Payment for technical services, Contingencies, Administrative costs
Achievements
Stage
10% Cash Contribution
(Rs.)
20% Labour Contribution
(Rs.)
Fund received from
other sources
Gemidirya Contribution
(Rs.)
1st Stage
55,601.00
0.00
0.00
593,410.00
2nd Stage
78,729.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total
134,330.00
0.00
0.00
593,410.00
Current Status
Stage 1:
Completed.
Stage 2:
80% on going.
Stage 3:
Infrastructure sub project 5
Title of Sub Project:
Reasons for Selecting this Project :
Estimates
Stage of Construction
Total Estimate (Rs.)
10% Cash Contribution (Rs.)
20% Labour Contribution (Rs.)
No: of Labour Days
Gemidirya Contribution (Rs.)
Labour
Goods
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
Total
0.00
0.00
0.00
0.00
0
0.00
Total Estimate Includes Civil works, Training, Payment for technical services, Contingencies, Administrative costs
Achievements
Stage
10% Cash Contribution
(Rs.)
20% Labour Contribution
(Rs.)
Fund received from
other sources
Gemidirya Contribution
(Rs.)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total
0.00
0.00
0.00
0.00
Current Status
Stage 1:
Completed.
Stage 2:
80% on going.
Stage 3:
Infrastructure sub project 6
Title of Sub Project:
Reasons for Selecting this Project :
Estimates
Stage of Construction
Total Estimate (Rs.)
10% Cash Contribution (Rs.)
20% Labour Contribution (Rs.)
No: of Labour Days
Gemidirya Contribution (Rs.)
Labour
Goods
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
Total
0.00
0.00
0.00
0.00
0
0.00
Total Estimate Includes Civil works, Training, Payment for technical services, Contingencies, Administrative costs
Achievements
Stage
10% Cash Contribution
(Rs.)
20% Labour Contribution
(Rs.)
Fund received from
other sources
Gemidirya Contribution
(Rs.)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total
0.00
0.00
0.00
0.00
Current Status
Stage 1:
Completed.
Stage 2:
80% on going.
Stage 3:
Infrastructure sub project 7
Title of Sub Project:
Reasons for Selecting this Project :
Estimates
Stage of Construction
Total Estimate (Rs.)
10% Cash Contribution (Rs.)
20% Labour Contribution (Rs.)
No: of Labour Days
Gemidirya Contribution (Rs.)
Labour
Goods
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
Total
0.00
0.00
0.00
0.00
0
0.00
Total Estimate Includes Civil works, Training, Payment for technical services, Contingencies, Administrative costs
Achievements
Stage
10% Cash Contribution
(Rs.)
20% Labour Contribution
(Rs.)
Fund received from
other sources
Gemidirya Contribution
(Rs.)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total
0.00
0.00
0.00
0.00
Current Status
Stage 1:
Completed.
Stage 2:
80% on going.
Stage 3:
Infrastructure sub project 8
Title of Sub Project:
Reasons for Selecting this Project :
Estimates
Stage of Construction
Total Estimate (Rs.)
10% Cash Contribution (Rs.)
20% Labour Contribution (Rs.)
No: of Labour Days
Gemidirya Contribution (Rs.)
Labour
Goods
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
0.00
0.00
0.00
0.00
0
0.00
Total
0.00
0.00
0.00
0.00
0
0.00
Total Estimate Includes Civil works, Training, Payment for technical services, Contingencies, Administrative costs